What Is a Catch-Up Plan?
A catch-up plan (also called a recovery programme or acceleration schedule) is a formal written document submitted by a Contractor or Consultant to the Client (RAB) explaining how they intend to recover lost time or progress and return to the approved project baseline schedule.
When Should a Catch-Up Plan Be Requested?
A catch-up plan should be requested proactively โ not only when a project is severely delayed. The table below maps key trigger events to the required response:
Trigger Thresholds โ Quick Reference
These thresholds are based on the Physical Variance % (column Q in the BOQ: Phy.Actual% โ Phy.Planned%) and missed milestones visible in the portal:
What the Catch-Up Plan Must Contain
A valid, reviewable catch-up plan must address 8 core elements. A plan missing any of these should be rejected and returned for revision within 48 hours:
- ! Clear identification of why progress has fallen behind (not just "weather" or "logistics")
- ! Categorised causes: design changes, material delays, workforce issues, equipment breakdown, site access, cash flow
- ! Identification of which cause is the contractor's responsibility vs. which is an employer's risk
- ! Supporting evidence: delivery records, weather logs, meeting minutes, variation order references
- % Actual physical progress % per work section (matching BOQ sections)
- % Planned progress % at the date of submission
- % Variance % per section and overall
- ๐ List of milestones that are overdue with days delayed
- ๐ฐ Financial expenditure to date vs. planned expenditure
- ๐ A revised bar chart / Gantt showing activities, durations, and completion dates
- ๐ The original baseline programme shown alongside the revised programme (so variance is visible)
- ๐ Revised milestones with new target dates
- ๐ Critical path clearly identified โ which activities must not slip further
- โ New planned completion date โ and whether it meets the contractual completion date
- ๐ท Additional workforce numbers and specialisations to be deployed, by week
- ๐ Additional plant and equipment to be brought to site (type, quantity, arrival date)
- ๐งฑ Material procurement and delivery schedule โ what is on order, expected delivery dates
- ๐ Sub-contractor engagement plan if specialist works are involved
- ๐ Week-by-week production targets for each BOQ section (e.g. "Week 1: 120 mยณ earthworks")
- ๐ Monthly cumulative physical progress % targets that lead back to plan
- โ S-curve showing how the revised plan converges back to the baseline
- ๐ KPIs the supervisor will measure weekly (e.g. "no. of workers on site", "mยณ concrete cast per day")
- ๐ฐ Evidence that contractor has sufficient cash flow to fund acceleration (bank statement or letter from financier)
- ๐ฐ Confirmation that any outstanding payment certificates have been submitted
- ๐ฐ Breakdown of additional costs for acceleration (overtime, extra plant, expedited materials) and who bears them
- ๐ฆบ Confirmation that acceleration will not compromise quality standards or safety
- ๐ฆบ Additional QA/QC inspection points if works are accelerated
- ๐ฆบ Updated Health & Safety plan for the increased workforce
- โ Signed by the Contractor's authorised representative / Site Manager
- โ Countersigned / reviewed by the Supervision Consultant before submission to RAB
- ๐
Dated and referenced (e.g.
CDAT-KRW-CATCHUP-001) - ๐ Uploaded to the portal as an attachment under Issues & Risks section of the site window
How the Plan Should Be Structured (Step-by-Step Flow)
Sample Catch-Up Plan Cover Letter Template
The following is a template for the formal cover letter / submission memo that accompanies the full catch-up plan document:
Catch-Up Plan Submission Letter
Date: [DD/MM/YYYY]
To: RAB CDAT Programme Manager โ Rwanda Agriculture Board
Through: [Supervision Consultant Name & Firm]
From: [Contractor Name & Firm]
Subject: Catch-Up Plan โ [Site Name] Irrigation Scheme โ Contract No. [Contract No.]
We refer to your written notice dated [date of notice] (Ref: [notice ref]) regarding progress delay on the above-referenced project, and hereby submit our Catch-Up Plan in accordance with Clause [contract clause no.] of the Contract.
As at [date], physical progress stands at [X]% against a planned progress of [Y]%, representing a variance of [โZ]%.
The delay is primarily attributable to: [brief cause description โ e.g. "delayed delivery of HDPE pipes due to supply chain disruption and extended wet season"]. A detailed root cause analysis is provided in Section B of the attached plan.
We propose to recover the delay by: [e.g. "deploying an additional 25 skilled labourers from Week 12, procuring one additional excavator, working extended daily hours of 10 hours/day and introducing Saturday works"]. Detailed weekly targets are set out in Section F of the attached plan.
With the proposed measures, we commit to achieving practical completion by [revised date], which is [X weeks] [ahead of / in line with / beyond] the contractual completion date of [original date].
We commit to submitting weekly progress reports against the targets in this plan and to convene a recovery progress meeting every [fortnight / week] with the Supervision Consultant.
Name: [Authorised Representative] Position: [Title]
Signature: _________________________ Date: [DD/MM/YYYY]
Reviewed by (Supervision Consultant):
Name: [Consultant Name] Position: [Title]
Signature: _________________________ Date: [DD/MM/YYYY]
Good Plan vs. Bad Plan โ What to Accept and Reject
| Aspect | โ Accept (Good Plan) | โ Reject (Insufficient Plan) |
|---|---|---|
| Root Cause | "HDPE pipe delivery delayed by 3 weeks due to supplier stock shortage. Evidence: delivery note DN-045 showing revised date." | "Works were delayed due to bad weather and procurement issues." โ No specifics, no evidence. |
| Programme | Revised Gantt chart with baseline overlay, critical path marked, new milestone dates for each work section. | "We will work faster." No revised schedule provided. |
| Resources | "20 additional labourers arrive Week 12. 1 additional excavator arriving 15 May. Confirmed by purchase order PO-2026-087." | "We will deploy more workers." No numbers, no dates, no confirmation. |
| Weekly targets | Week 12: 180 mยณ earthworks, 45 m canal lining. Week 13: 200 mยณ earthworks, 60 m canal lining. | No weekly targets โ only a new overall completion date. |
| Completion date | States a specific revised date and explains whether an EOT will be claimed or liquidated damages accepted. | Vague โ "We expect to finish on time." No revised date or contractual position stated. |
| Signatures | Signed by Contractor's Resident Engineer + countersigned by Supervision Consultant. | Unsigned or signed only by a junior site officer with no consultant review. |
| Financial | Includes bank confirmation letter or statement showing funds available for acceleration costs. | No mention of how acceleration will be funded โ risk of plan not being implemented. |
Monitoring the Plan After Submission
Submitting and approving a catch-up plan is only the beginning. The Supervision Consultant and RAB must actively track performance against it:
- Update Qty Done (col R) in the BOQ Excel โ re-import โ check variance
- Record milestone status in the portal
- Site supervisor submits a 1-page weekly progress note vs. catch-up targets
- Recovery meeting: Contractor + Consultant + RAB PM
- Compare actual vs. catch-up plan targets
- Update portal Issues & Risks if variance is worsening
- Monthly progress report includes catch-up plan performance section
- If plan is not being met after 4 weeks โ escalate to Show Cause
- Update Gantt in portal โ revise milestone dates if recovery is on track
How to Record & Track in the RAB Irrigation Portal
The portal already has the tools needed to monitor catch-up plan status. Here is how to use them:
โ Open the site in Physical Construction โ Execution Phase โ Export Excel โ check Column Q (Phy.Variance%) across all BOQ sections.
โ In the Issues & Risks section of the Execution Phase window, add a High severity issue recording: the variance %, the date of notice, and the catch-up plan reference number.
target_date to match the revised dates in the approved catch-up plan:Frequently Asked Questions
At-a-Glance Decision Chart
| Physical Variance % | Missed Milestone? | Action Required | Response Deadline | Who Acts |
|---|---|---|---|---|
| 0% to โ3% | No | Monitor only. Note in monthly report. | Next monthly report | Site Supervisor |
| โ3% to โ5% | Maybe | Verbal warning. Increased inspection frequency. | Next site meeting | Supervision Consultant |
| โ5% to โ10% | Yes โ minor | Written notice. Catch-up plan required. | 7 days to submit plan | Supervision Consultant + RAB PM |
| โ10% to โ20% | Yes โ major | Formal contractual notice. Full plan with revised Gantt required. | 7 days + RAB Contract Mgr | RAB Contract Manager |
| Below โ20% | Yes โ critical | Show Cause Notice. Performance security review. | 5 days + Management | RAB Senior Management |
| Any % | Yes โ overdue | Automatic written early warning regardless of overall %. | Immediate | Supervision Consultant |